Red Bluff Road Evacuation Route
Projects Details
Project Name
Red Bluff Road Evacuation Route
Description
Construct a 4-lane road with curb and gutter and bridge from Kirby Blvd to Hwy 146. 
Location
Taylor Lake Village
Type of Project
Street & Traffic
Estimated Cost
$9,000,000
Construction Start
4th Qtr, 2019
Construction Completion
3rd Qtr, 2021
Current Status
Construction